Britton Lumber Combined Heat and Power Project

Bath, NH

Britton Lumber is installing a new biomass combined heat and power plant that required a building addition.  We chose to go with Glulam beams/columns with a CLT roof system. 

Version History
  • Project last updated by WoodWorks on 12-11-2024
Project Details
  • Year Built

    2024

  • Number Of Stories

    1

  • Bldg system

    Mass Timber

  • Square footage

    2275

  • Construction Type:

    Unknown

  • Building Type:

    Factory/Industrial (warehouse, storage, parking, etc.)

  • Material Types:

    Mass Timber
    Cross-Laminated Timber (CLT)
    Glue-Laminated Timber (GLT or glulam)
    Hybrid (wood with steel or concrete)
    Structural Composite Lumber (e.g. LVL and LSL)
    Lumber

Project Team
  • E.F. Wall & Assoc. Inc General Contractor
  • Ricky McLain Mass Timber Advisor
  • Wilson Engineering Services Owners Engineer